Appointed as Principal Contractor, the 15 week project began with the demolition of the existing sales shop; to facilitate the build of a brand new kiosk, new control room and associated forecourt.


“Another great scheme landed by Bryan and his team, Nick has been a fantastic site manager, the project finished on time which is a great effort considering the ground conditions we had on this site.”
Retail Asset Manager
Asda
Asda, Kettering
The site team overcame the challenge of poor ground conditions by using piled foundations for the canopy and a cofferdam for the new tank; thereby engineering out the need for a second cofferdam to remove the existing tank farm.
Through hard work by the site team to overcome the project challenges, the programme of works was successfully completed as scheduled and delivered significant cost savings to the client. The project was handed over on time to our enthusiastic client who was once again delighted with Toureen’s high standard of workmanship and commended our team on site.
Our work included:
- Removal of concrete forecourt surface in order to extract 6 existing fuel tanks
- Installation of two new 75,000L fuel tanks with new fuel lines, drainage and a new 10,000L class 1 interceptor
- Refurbishment of existing car wash and jet wash machine
- Installation of new forecourt, complete with four new pump islands
Project details
Client
Asda
Division
Fuel Systems
Sector
Oil & Fuels
Duration
15 weeks